900 East; 900 South To 2100 South

crane

900 East; 900 South To 2100 South


Owner: Utah Department of Transportation

The project scope of work consisted of road-asphalt rehabilitation over 900 East from 900 South to 2100 South. In some sections sidewalk and curb and gutter was replaced, storm drain line, irrigations system, rotomill, overlay and signal improvement was installed along the project. The project was subdivided in 3 work zones, most of the scope of work in each zone had to be mostly completed before moveing to the next one. The project started on Tuesday, November 18th, 2008. It took 380 calendar days to complete. We completed all the irrigation system work by April 1st, 2009 in the whole length of the project.